Newton of Culvie is a single Enercon E-48 site located near Aberchirder, Aberdeenshire. The turbine became operational on 22nd September 2015. Total construction time was 6 months and managed by our Project Engineer Chris Dall. The site is a joint venture between Muirden Energy and the land owner Leslie Watson.

Where possible, Muirden Energy endeavours to support the local economy at our turbine sites by using locally sourced contractors. At this site Scotplant (Hire) Ltd was the civils contractor with Prelec Ltd as the electricals contractor.